Question: Problem 4 - 7 ( Static ) The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (
Problem Static
The following activities are part of a project to be scheduled using CPM:
ACTIVITY IMMEDIATE PREDECESSOR TIME WEEKS
A
B A
C A
D C
E B D
F D
G E F
b What is the critical path?
multiple choice
ABEG
ACDFG
ACDEG
c How many weeks will it take to complete the project?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock