Question: Problem 4 - 7 ( Static ) The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (

Problem 4-7(Static)
The following activities are part of a project to be scheduled using CPM:
ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS)
A 6
B A 3
C A 7
D C 2
E B, D 4
F D 3
G E, F 7
b. What is the critical path?
multiple choice
A-B-E-G
A-C-D-F-G
A-C-D-E-G
c. How many weeks will it take to complete the project?

Step by Step Solution