TIMES (DAYS)
ACTIVITYIMMEDIATE
PREDECESSORSambA147B3510CA258DA4611EB123FC, D357GD, E126HF, G256
b.What is the critical path?
multiple choice
A-D-G-H
A-D-F-H Correct
A-C-F-H
B-E-G-H
c.
What is the expected project completion time? (Do not round intermediate calculations. Round your answer to 3 decimal places.)
Project completion time20.167 Numeric ResponseEdit Unavailable. 20.167 correct.days
d.
What is the probability of completing this project within 22 days?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!