Question: Problem 5-10 (Algo) The following represents a project that should be scheduled using CPM: IMMEDIATE PREDECESSORS TIMES (DAYS) ACTIVITY a m b A 1 4

Problem 5-10 (Algo)

The following represents a project that should be scheduled using CPM:

IMMEDIATE PREDECESSORS TIMES (DAYS)
ACTIVITY a m b
A 1 4 7
B 1 3 5
C A 2 5 11
D A 1 8 9
E B 1 2 3
F C,D 1 6 11
G D,E 1 2 3
H F,G 2 3 3

b. What is the critical path?

a. A-D-F-H

b. B-E-G-H

c.A-D-G-H

d.A-C-F-H

c. What is the expected project completion time? (Do not round intermediate calculations. Round your answer to 3 decimal places.)

d. What is the probability of completing this project within 22 days? (Use Excel's NORM.S.DIST() function to find the correct probability for your computed Z-value. Do not round intermediate calculations. Round "z" value to 2 decimal places and final answer to 4 decimal places.)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!