Question: Problem 4. (Chapter 7 Capacity Planning) Up, Up, and Away is a producer of kites and wind socks. Relevant data on a bottleneck operation in
Problem 4. (Chapter 7 Capacity Planning) Up, Up, and Away is a producer of kites and wind socks. Relevant data on a bottleneck operation in the shop for the upcoming fiscal year are given in the following table: (Hint: This problem is similar to the example in Slides 11-16 of Chapter 7 ) The shop works two shifts per day, 8 hours per shift, 200 days per year. Currently, the company operates four machines, and desired a 25 percent capacity cushion. How many machines should be purchased to meet the upcoming year's demand without resorting to any short-term capacity solutions