Question: Problem 4: MRP Calculations (9 points) The low-level coded BOM is shown in the attached Excel file along with a template to complete for parts
Problem 4: MRP Calculations (9 points)
The low-level coded BOM is shown in the attached Excel file along with a template to complete for parts A, B and C. The on hand (OH), lead time (LT), safety stock (SS), and production lot size (Q) are shown for each item. Marketing has a gross requirement for 100 part A in week 8. There are scheduled receipts of 50 B in week 1 and 200 C in week 2.
- Complete the sections highlighted in yellow on the template for part A. (3 points)
- Complete the sections highlighted in yellow on the template for part B. (3 points)
- Complete the sections highlighted in yellow on the template for part C. (3 points)
Below I am providing you with the MRP template that must be filled out and used for this problem.