Question: Problem 4 The float is the amount of time an activity can be delayed without delaying the: Project. Completion date required by the customer. Early
Problem 4
The float is the amount of time an activity can be delayed without delaying the:
Project.
Completion date required by the customer.
Early start of its successor. Project completion date.
Problem 5
A planned cost of a project is $15,000 and the actual cost to date is $10,000 so far and the value completed is only 50 percent. What is the schedule variance?
-$7,500
$7,500
-$5,000
$5,000