The float is the amount of time an activity can be delayed without delaying the:

Project.

Completion date required by the customer.

Early start of its successor. Project completion date.

Problem 5

A planned cost of a project is $15,000 and the actual cost to date is $10,000 so far and the value completed is only 50 percent. What is the schedule variance?

-$7,500

$7,500

-$5,000

$5,000