Question: Total float is the amount of time an activity can be delayed without delaying the Group of answer choices Project completion date Early start of
Total float is the amount of time an activity can be delayed without delaying the
Group of answer choices
Project completion date
Early start of its successor
Completion date required by the customer
Project