Question: Problem 4 : The table below gives the activity duration and precedence relationships for a small project consisting o f six activities. Also shown i

Problem 4:
The table below gives the activity duration and precedence relationships for a small project consisting of six activities. Also shown is the cost per day of crashing each activity and the maximum number of days that each activity may be crashed.
Activity
Predecessor
Normal Time (days)
Maximum Crashing (days)
$day
1
??
9
5
5000
2
??
7
3
6000
3
1
5
3
4000
4
1,2
8
4
2000
5
3
6
3
3000
6
4,5
9
5
9000
Determine which activities should be crashed, and by how much, to complete the project in22 days.
Suppose there isno specific completion time but that there is a payment of $5000 for each day that the project duration is reduced below the normal completion time. Determine the optimum number of days to complete the project and which activities would be crashed and by how many days.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!