Question: Problem 4 : The table below gives the activity duration and precedence relationships for a small project consisting o f six activities. Also shown i
Problem :
The table below gives the activity duration and precedence relationships for a small project consisting six activities. Also shown the cost per day crashing each activity and the maximum number days that each activity may crashed.
Activity
Predecessor
Normal Time
Maximum Crashing
Determine which activities should crashed, and how much, complete the project days.
Suppose there specific completion time but that there a payment $ for each day that the project duration reduced below the normal completion time. Determine the optimum number days complete the project and which activities would crashed and how many days.