The table below gives the activity duration and precedence relationships for a small project consisting of six
Fantastic news! We've Found the answer you've been seeking!
Question:
Determine which activities should be crashed, and by how much, to complete the project in 22 days.
Suppose there is no specific completion time but that there is a payment of dollar 5000 for each day that the project duration is reduced below the normal completion time. Determine the optimum number of days to complete the project and which activities would be crashed and by how many days.