Question: Problem 5 - 1 0 ( Algo ) The following represents a project that should be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSORS TIMES ( DAYS

Problem 5-10(Algo)
The following represents a project that should be scheduled using CPM:
ACTIVITY IMMEDIATE PREDECESSORS TIMES (DAYS)
a m b
A 123
B 147
C A 2811
D A 159
E B 123
F C,D 147
G D,E 123
H F,G 233
What is the critical path?
multiple choice
A-D-G-H
A-D-F-H
B-E-G-H
A-C-F-H
What is the expected project completion time?
Note: Do not round intermediate calculations. Round your answer to 3 decimal places.

Step by Step Solution