Question: Problem 4-8 The following represents a project that should be scheduled using CPM: UseAppendix G. TIMES (DAYS) ACTIVITY IMMEDIATE PREDECESSORS a m b A 1
Problem 4-8
| The following represents a project that should be scheduled using CPM: UseAppendix G. |
| TIMES (DAYS) | ||||
| ACTIVITY | IMMEDIATE PREDECESSORS | a | m | b |
| A | 1 | 4 | 7 | |
| B | 3 | 5 | 10 | |
| C | A | 2 | 5 | 8 |
| D | A | 4 | 6 | 11 |
| E | B | 1 | 2 | 3 |
| F | C, D | 3 | 5 | 7 |
| G | D, E | 1 | 2 | 6 |
| H | F, G | 2 | 5 | 6 |
| b. | What is the critical path? | ||||
|
| c. | What is the expected project completion time?(Do not round intermediate calculations. Round your answer to 3 decimal places.) |
| Project completion time | days |
| d. | What is the probability of completing this project within 22 days?(Use Excel's NORMSDIST() function to find the correct probability for your computedZ-value. Do not round intermediate calculations. Round "z" value to 2 decimal places and final answer to 4 decimal places.) |
| Probability |
b. The critical path is A D F H
c. The Expected project time is 20.166 days
d. I cannot figure out (d) can you help me with this one?
Thank you!