Question: Problem 5 . 1 7 ( Static ) The following CPM network has estimates of the normal time in weeks listed for the activities: a
Problem Static
The following CPM network has estimates of the normal time in weeks listed for the activities:
a Determine the critical path.
ABEG
ACFG
ACEG
ABDG
a Determine the early completion time in weeks for the project.
Early completion time
weeks
For the data shown, reduce the project completion time by three weeks. Assume a linear cost per week shortened.
b Which activitles in order of reduction would be shortened?
GDA
DGA
DBC
AGD
b Find the resulting cost to crash.
Resulting cost to crash