Question: Problem 5 - 4 ( Algo ) The Carry - on Luggage Company must set up an assembly line for a wheeled carry - on
Problem Algo
The Carryon Luggage Company must set up an assembly line for a wheeled carryon bag. Forecasts show that units per hour should be produced. The tasks required, task times, and precedence relationships are as follows:
tableTaskTime secondsPredecessorsABACADBEBFBGC E FHD G
pictureClick here for the Excel Data File
a What is the takt time?
b What is the theoretical number of workstations?
c Assign the tasks to the workstations to balance the line using the longest operating time rule.
d What is the efficiency of the balanced line?