Question: Problem 5 - 7 ( Algo ) Williams Motor Manufacturing assembles small motors for sale to major appliance manufacturers around the world. Average demand for
Problem Algo
Williams Motor Manufacturing assembles small motors for sale to major appliance manufacturers around the world. Average demand for its bestselling motor is units per day. The assembly line operates continuously during a single hour shift. The tasks required, task times, and precedence relationships are:
DictureClick here for the Excel Data File
a What is the takt time?
b What is the theoretical number of workstations?
c Assign the tasks to the workstations to balance the line using the longest operating time rule.
d What is the efficiency of the balanced line?
e If demand increased to motors per day, what would be the new takt time?
Required A
Required B
Required C
Required D
Required E
Assign the tasks to the workstations to balance the line using the longest operating time
Workstation Tasks in Order
Workstation Time seconds
Idle Time seconds grad
I just need help on part c And d
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock