Question: PROBLEM - 5 DRAW A PRECEDENCE NETWORK FOR A REINFORCED CONCRETE CULVERT PROJECT FROM THE ACTIVITIES AND DURATIONS LISTED BELOW. table [ [ ACTIVITIES

PROBLEM -5
DRAW A PRECEDENCE NETWORK FOR A REINFORCED CONCRETE CULVERT PROJECT FROM THE ACTIVITIES AND DURATIONS LISTED BELOW.
\table[[ACTIVITIES,DURATION (DAYS)],[EXCAVATION,1],[REINFORCE BASE,2],[SHUTTER BASE,2 BEINGS 1 DAY AFTER REINFORCING BEGINS.],[CONCRETE BASE,1],[REINFORCE N. WALL,2],[SHUTTER N. WALL,2 BEINGS 1 DAY AFTER REINFORCING BEGINS.],[CONCRETE N. WALL,1],[REINFORCE S. WALL,1],[SHUTTER S. WALL,1],[CONCRETE S. WALL,1],[SCABBLE N. WALL TOP,1 FOLLOWS CONCRETING OF RELEVANT WALLS.],[SCABBLE S. WALL TOP,1 FOLLOWS CONCRETING OF RELEVANT WALLS.],[SHUTTER ROOF,2],[REINFORCE ROOF,2 BEGINS 1 DAY AFTER SHUTTERING STARTS.],[FIX H. D. BOLTS,1 BEGINS 1 DAY AFTER SHUTTERING STARTS.],[CONCRETE ROOF SLAB,1 FOLLOWS ALL OTHER ACTIVITIES.]]
PROBLEM - 5 DRAW A PRECEDENCE NETWORK FOR A

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!