Question: Problem 5.1. Using the project data in Exhibit 5.66, do the following: a. Draw the CPM network for the project. b. Enumerate the paths through

Problem 5.1. Using the project data in Exhibit
Problem 5.1. Using the project data in Exhibit 5.66, do the following: a. Draw the CPM network for the project. b. Enumerate the paths through the network. c. Using the CPM algorithm, calculate the early and late start schedules (ie. early start and early finish times, and late start and late finish times) d. Identify the critical path(s) Exhibit 5.66 Task Data for Six-Task Project Exhibit 5.66 Task Data for Six- Task Project Task Duration Predecessors Start 0 A 56 Start B 23 A 34 A D 34 B E 58 CD F 47 D End 0 EF