Question: Problem 5-10 (Algo) The following represents a project that should be scheduled using CPM: TIMES (DAYS) b ACTIVITY ABCDEFGH IMMEDIATE PREDECESSORS AABCDE C, D D,

Problem 5-10 (Algo) The following represents a project that should be scheduled using CPM: TIMES (DAYS) b ACTIVITY ABCDEFGH IMMEDIATE PREDECESSORS AABCDE C, D D, E F, G b. What is the critical path? OA-C-F-H A-D-G-H O A-D-F-H OB-E-G-H a 1 Project completion time 1 3 1 1112 52542253 6 9 3 7 93280 10 12 c. What is the expected project completion time? Note: Do not round intermediate calculations. Round your answer to 3 decimal places. days
 Problem 5-10 (Algo) The following represents a project that should be
scheduled using CPM: TIMES (DAYS) b ACTIVITY ABCDEFGH IMMEDIATE PREDECESSORS AABCDE C,
please help with c and d

The following represents a project that should be scheduled using CPM: b. What is the critical path? A.C.F.HA.D.G.HA.D.F.HB-E.G.H c. What is the expected project completion time? Note: Do not round intermediate calculations. Round your answer to 3 decimal places. b. What is the critical path? A.C.F.H A.D.GH ADF.H B-E.GH c. What is the expected project completion time? Note: Do not round intermediate calculations. Round your answer to 3 decimal places. d. What is the probability of completing this project within 20 days? Note: Use Excer's NORM.S.OIST function to find the correct probability for your computed Z value. Do not round intermediate calculations. Round Z value to 2 decimal ploces and final answer to 4 decimal places

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!