Question: Problem 4-10 (Static) The following represents a project that should be scheduled using CPM: TIMES (DAYS) ACTIVITY A B C G H A-D-G-H A-C-F-H A-D-F-H
The following represents a project that should be scheduled using CPM: b. What is the critical path? A-D-G-H A.C.F.H A-D.F.H B-E-G.H c. What is the expected project completion time? Note: Do not round intermediate calculations. Round your answer to 2 decimal places. d. What is the probability of completing this project within 16 days? Note: Use Excel's NORMSDIST(0) function to find the correct probability for your computed Z-value. Do not round intermediate calculations. Round " z " value to 2 decimal places and final answer to 4 decimal places