Question: Problem 4-10 (Static) The following represents a project that should be scheduled using CPM: TIMES (DAYS) ACTIVITY A B C G H A-D-G-H A-C-F-H A-D-F-H

Problem 4-10 (Static) The following represents a project that should be scheduled using CPM: TIMES (DAYS) ACTIVITY A B C G H A-D-G-H A-C-F-H A-D-F-H OB-E-G-H IMMEDIATE PREDECESSORS A A B b. What is the critical path? C,D D,E F,G Probability Project completion time a 1 1 1 2 3 3 1 2 Emr 0.8677 m 3 2 2 3 4444 c. What is the expected project completion time? Note: Do not round intermediate calculations. Round your answer to 2 decimal places. 10.50 days b 11 d. What is the probability of completing this project within 16 days? Note: Use Excel's NORMSDIST() function to find the correct probability for your computed Z-value. Do not round intermediate calculations. Round "z" value to 2 decimal places and final answer to 4 decimal places.
 Problem 4-10 (Static) The following represents a project that should be

The following represents a project that should be scheduled using CPM: b. What is the critical path? A-D-G-H A.C.F.H A-D.F.H B-E-G.H c. What is the expected project completion time? Note: Do not round intermediate calculations. Round your answer to 2 decimal places. d. What is the probability of completing this project within 16 days? Note: Use Excel's NORMSDIST(0) function to find the correct probability for your computed Z-value. Do not round intermediate calculations. Round " z " value to 2 decimal places and final answer to 4 decimal places

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!