Question: Problem 5-10 (Algo) The following represents a project that should be scheduled using CPM: IMMEDIATE ACTIVITY PREDECESSORS A B A D E B F C,D

Problem 5-10 (Algo) The following represents a
Problem 5-10 (Algo) The following represents a
Problem 5-10 (Algo) The following represents a project that should be scheduled using CPM: IMMEDIATE ACTIVITY PREDECESSORS A B A D E B F C,D G DE F G TIMES (DAYS) a m b 1 1 4 4 5 6 3 7 11 1 2 9 6 8 2 12 10 10 NNH b. What is the critical path? A-D-G-H O A-D-F-H O A-C-F-H B-E-G-H c. What is the expected project completion time? (Do not round Intermediate cal Project completion time days