Question: Problem 5-12 The following table represents a plan for a project: PREDECESSOR JOB(S) TIMES (DAYS) JOB NO. a m b 1 1 2 6 2

Problem 5-12

The following table represents a plan for a project:

PREDECESSOR JOB(S) TIMES (DAYS)
JOB NO. a m b
1 1 2 6
2 1 3 8 13
3 1 4 4 13
4 1 1 3 8
5 2 2 5 8
6 3 2 5 11
7 4 4 8 9
8 5,6 1 5 6
9 8 1 4 13
10 7 3 4 5
11 9,10 5 5 8

b. Indicate the critical path.

  • A) 1-4-7-10-11
  • B) 1-3-6-8-9-11
  • C) 1-2-5-8-9-11
  • D) 1-2-5-8

c. What is the expected completion time for the project? (Round your answer to 2 decimal places.)

Expected completion time ______ days

d. You can accomplish any one of the following at an additional cost of $1,500 and if you will save $1,000 for each day that the earliest completion time is reduced, which action, if any, would you choose?

1. Reduce job 4 by two days.

  • Yes

  • No

2. Reduce job 2 by four days.

  • No

  • Yes

3. Reduce job 9 by four days.

  • Yes

  • No

e. What is the probability that the project will take more than 34 days to complete? (Round your answer to 2 decimal places.)

Probability _____

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!