Question: Problem 5-12 The following table represents a plan for a project: PREDECESSOR JOB(S) TIMES (DAYS) JOB NO. a m b 1 1 3 8 2

Problem 5-12

The following table represents a plan for a project:

PREDECESSOR JOB(S) TIMES (DAYS)
JOB NO. a m b
1 1 3 8
2 1 3 3 6
3 1 3 6 12
4 1 5 7 12
5 2 3 6 12
6 3 1 2 3
7 4 2 9 10
8 5,6 2 4 6
9 8 2 4 12
10 7 4 4 7
11 9,10 2 11 11

b. Indicate the critical path.

1-4-7-10-11
1-2-5-8
1-2-5-8-9-11
1-3-6-8-9-11

c. What is the expected completion time for the project? (Round your answer to 2 decimal places.)

Expected completion time days

d. You can accomplish any one of the following at an additional cost of $2,000 and if you will save $1,500 for each day that the earliest completion time is reduced, which action, if any, would you choose?

1. Reduce job 6 by two days.

No
Yes

2. Reduce job 4 by two days.

Yes
No

3. Reduce job 9 by two days.

Yes
No

e. What is the probability that the project will take more than 35 days to complete? (Round your answer to 2 decimal places.)

Probability

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!