Question: Problem 5-14 (Static) Here is a CPM network with activity times in weeks: (B(5) C(6) A(7) G(3) D(6) E(4) (F(8) a. Determine the critical path

Problem 5-14 (Static) Here is a CPM network with
Problem 5-14 (Static) Here is a CPM network with
Problem 5-14 (Static) Here is a CPM network with activity times in weeks: (B(5) C(6) A(7) G(3) D(6) E(4) (F(8) a. Determine the critical path O AE-GC-D O A-E-F-D O A-B-C-D b. How many weeks will the project take to complete? Number of weeks c. Suppose Fcould be shortened by two weeks and B by one week. By how many weeks would this reduce the project duration? Number of weeks reduced