Question: Based on the following table, and using the PERT technique answer the next questions. Activity a m b A 4 6 10 B 2 4
Based on the following table, and using the PERT technique answer the next questions.
| Activity | a | m | b |
| A | 4 | 6 | 10 |
| B | 2 | 4 | 6 |
| C | 6 | 6 | 7 |
| D | 10 | 12 | 12 |
| E | 4 | 7 | 8 |
| F | 5 | 8 | 10 |
| G | 3 | 5 | 7 |
| H | 7 | 9 | 12 |
| I | 8 | 10 | 14 |
The value of for activity D is ___.
11
12
15
18
The value of ^2 for activity I is ___.
.30
.45
.55
1.00
The Critical Path of the project using is ___.
A, C, F, H
A, B, F, H
A, B, C, F, H
A, B, C, F, H, I
The probability of finish the project in 30 days or less is ___.
57%
62%
70%
74%
PERT assumes that the duration of each activity is a random variable with unknown mean and standard variation.
True
False