Question: Problem 5-15 Here is a network with the activity times shown in days: a. Determine the critical path. A-C-D-F-G A-B-D-F-G A-B-D-E-G A-C-D-E-G ACDFG The following

Problem 5-15

Here is a network with the activity times shown in days:

a. Determine the critical path.

A-C-D-F-G
A-B-D-F-G
A-B-D-E-G
A-C-D-E-G

ACDFG

The following table shows the normal times and the crash times, along with the associated costs for each activity.

ACTIVITY NORMAL TIME CRASH TIME NORMAL COST CRASH COST
A 5 4 $ 7,100 $ 9,000
B 4 3 5,100 7,100
C 7 5 9,100 11,200
D 7 6 3,300 4,300
E 3 2 2,300 3,300
F 8 7 4,100 6,000
G 4 3 5,200 8,300

b-1. If the project is to be shortened by four days, which activities, in order of reduction, would be shortened? (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer.)

A, C (or E), F (or A)
D, C, C, A (or F)
E, D
C, D (or E), F (or A)

DCCA(or F)

b-2. Find the resulting cost to crash.

Resulting cost $ ???

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!