Question: The following represents a project that should be scheduled using CPM:Here is a network with the activity times shown in days: A diagram shows a

The following represents a project that should be scheduled using CPM:Here is a network with the activity times shown in days:
A diagram shows a critical path through A, B, C, D, E, F and G.A diagram shows a critical path through A, B, C, D, E, F and G. It shows circles labeled as A (7), B (3), C (4), D (5), E (2), F (4) and (G (5). A is connected to B and C. B ad C are connected to D. D leads to F and E. F and E are connected to G.
a. Find the critical path.
multiple choice 1
A-B-D-F-G
A-C-D-F-G Correct
A-B-D-E-G
A-C-D-E-G
The following table shows the normal times and the crash times, along with the associated costs for each activity.
ACTIVITY NORMAL TIME CRASH TIME NORMAL COST CRASH COST
A 76 $7,000 $8,000
B 325,0007,000
C 439,00010,200
D 543,0004,500
E 212,0003,000
F 424,0007,000
G 545,0008,000
b-1. If the project is to be shortened by four days, which activities, in order of reduction, would be shortened?
multiple choice 2
A, C, D (or F), F (or D) Correct
A, F, D (or E)
E, A
C, F (or E), D (or E)
b-2. Find the resulting cost to crash.
the critical path?
multiple choice
A-C-F-H
A-D-F-H
B-E-G-H
A-D-G-H
What is the expected project completion time?
Note: Do not round intermediate calculations. Round your answer to 3 decimal places.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!