Question: Problem 5-15 (Static) Here is a network with the activity times shown in days: a. Find the critical path. A) A-B-D-E-G B) A-C-D-F-G C) A-C-D-E-G

Problem 5-15 (Static)

Here is a network with the activity times shown in days:

Problem 5-15 (Static) Here is a network with the

a. Find the critical path.

A) A-B-D-E-G

B) A-C-D-F-G

C) A-C-D-E-G

D) A-B-D-F-G

The following table shows the normal times and the crash times, along with the associated costs for each activity.

ACTIVITY NORMAL TIME CRASH TIME NORMAL COST CRASH COST
A 7 6 $ 7,000 $ 8,000
B 3 2 5,000 7,000
C 4 3 9,000 10,200
D 5 4 3,000 4,500
E 2 1 2,000 3,000
F 4 2 4,000 7,000
G 5 4 5,000 8,000

b-1. If the project is to be shortened by four days, which activities, in order of reduction, would be shortened?

  • A) A, F, D (or E)
  • B) A, C, D (or F), F (or D)
  • C) C, F (or E), D (or E)
  • D) E, A

b-2. Find the resulting cost to crash. Resulting cost to crash _______

B(3) D(5) F(4) A(7) G(5 (C(4) E(2)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!