Question: Problem 6 (10 points): Suppose there is an order for 300 of gear shaft SG 123. The due date is day 180. The route sheet,
Problem 6 (10 points):
Suppose there is an order for 300 of gear shaft SG 123. The due date is day 180. The route sheet, shown in Figure 1, gives information about the operations to be performed and the setup and run times. The work center file, shown in Figure 2, gives lead time data for each work center. Calculate the start and finish dates for each operation. Use the following scheduling rules.
a. Operation times are rounded up to the nearest 8 hours and expressed as days on a
one-shift basis. That is, if an operation takes 6.5 standard hours, round it up to 8 hours, which represents one day.
b. Assume an order starts at the beginning of the day and finishes at the end of a day. For example, if an order starts on day 1 and is finished on day 5, it has taken 5 days to complete. If move time is 1 day, the order will be available to the next workstation at the start of day 7.
Figure 1: Routing file
Part name: Gear shaft Part Number: SG 123
Drawing Number: D123X
Operation Work S/U Time Run Time/ Piece Operation
No. Center (Standard Hours) (Standard Hours)
10 12 1.50 0.20 Turn Shaft
20 14 0.50 0.25 Mill Slot
30 17 0.30 0.05 Drill 2 Holes
40 03 0.45 0.10 Grind
50 Stores Inventory
Figure 2: Lead time data from work center file.
Operation Number. Work Center Arrival Date Queue Operation Wait Finish Date
(days) (days) (days)
10 12 I. 3 A. 1 E.
20 14 J. 5 B. 1 F.
30 17 K. 2 C. 1 G.
40 03 L. 3 D. 1 H.
50 Stores 160
(a) Please fill in the blanks from A to L. (8 points)
(b) The order must arrive at work center 12 on which day? (2 points)
You can write down the procedure of calculation for problem 6 on this page.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
