Question: Problem 6-19 (Static) The following tasks are to be performed on an assembly line: TASK SECONDS TASKS THAT MUST PRECEDE A 20 B 7 A

Problem 6-19 (Static)

The following tasks are to be performed on an assembly line:

TASK SECONDS TASKS THAT MUST PRECEDE
A 20
B 7 A
C 20 B
D 22 B
E 15 C
F 10 D
G 16 E, F
H 8 G

The workday is seven hours long. Demand for completed product is 750 per day.

a. Find the cycle time required to meet the desired output rate. (Round your answer to 1 decimal place.)

b. What is the theoretical number of workstations required to meet the desired output rate? (Round up your answer to the next whole number.)

d. Balance the line using sequential restrictions and the longest-operating-time rule. (Round your answers to 1 decimal place.)

e. What is the efficiency of the line balanced as in part (d) assuming it is running at the cycle time determined in part (a)? (Round your answer to 1 decimal place.)

f. Suppose that demand rose from 750 to 800 units per day. What would you do? (Round your answer for cycle time down to the nearest whole number.)

g. Suppose that demand rose from 750 to 1,000 units per day. What would you do? (Round your answer for cycle time down to the nearest whole number.)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!