Question: Problem 7 in Niebel's Methods, Standards, & Work Design, 13th edition How many machines should be assigned to an operator for lowest-cost operations when: Loading
Problem 7 in Niebel's Methods, Standards, & Work Design, 13th edition
How many machines should be assigned to an operator for lowest-cost operations when:
Loading and unloading time on one machine is 1.41 min.
Walking time to the next facility is 0.08 min.
Machine time (power feed) is 4.34 min.
Operator rate is $13.20/h.
Machine rate is $18.00/h