Question: Problem 8 . Dranoff Corporation is currently working on ArtHaus Condo project with an estimated project budget of $ 3 . 5 Million and a

Problem 8.
Dranoff Corporation is currently working on ArtHaus Condo project with an estimated project budget of $3.5 Million and a planned duration of 24 months.
After 12 months, you have the following information about the project.
PV= $1,750,000
EV= $985,000
AC= $1,200,000
Calculate SV, CV, SPI, CPI, estimated time to completion, estimated cost to completion, and discuss the projects performance. (Method: Excel, Points: 10)
Time EV SV AC CV PV SPI CPI
12 months $985,000($765,000) $1,200,000($215,000) $1,750,0000.5628571430.820833333
Estimated time to completion =
estimated cost to completion =
3,063,959
$4,263,959

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!