Question: Problem 9 - 0 6 ( Algorithmic ) Consider the following project network and activity times ( in weeks ) : table [ [

Problem 9-06(Algorithmic)
Consider the following project network and activity times (in weeks):
\table[[Activity,A,B,C,D,E,F,G,H],[Time,4,5,10,7,7,2,10,7]]
a. Identify the critical path.
b. How much time will be needed to complete this project?
weeks.
Can artivitu F he dolaved withnut dolavinn the entire nrniert? If an hu how manv wiepke?