Question: Problem 9 - 1 2 ( Algorithmic ) Assume that the activity time estimates ( in days ) for the swimming pool construction project are

Problem 9-12(Algorithmic)
Assume that the activity time estimates (in days) for the swimming pool construction project are as follows:
Activity Optimistic Most Probable Pessimistic
A 234
B 159
C 249
D 4710
E 258
F 345
G 378
H 168
I 267
What are the critical activities? If necessary, round your answers to two decimal places. If your answer is zero, enter 0.
Earliest Latest Earliest Latest Critical
Activity Start Start Finish Finish Slack Activity
A fill in the blank 19
0
fill in the blank 20
fill in the blank 21
3
fill in the blank 22
fill in the blank 23
B fill in the blank 25
fill in the blank 26
fill in the blank 27
fill in the blank 28
fill in the blank 29
C fill in the blank 31
fill in the blank 32
fill in the blank 33
fill in the blank 34
fill in the blank 35
D fill in the blank 37
fill in the blank 38
fill in the blank 39
fill in the blank 40
fill in the blank 41
E fill in the blank 43
fill in the blank 44
fill in the blank 45
fill in the blank 46
fill in the blank 47
F fill in the blank 49
fill in the blank 50
fill in the blank 51
fill in the blank 52
fill in the blank 53
G fill in the blank 55
fill in the blank 56
fill in the blank 57
fill in the blank 58
fill in the blank 59
H fill in the blank 61
fill in the blank 62
fill in the blank 63
fill in the blank 64
fill in the blank 65
I fill in the blank 67
fill in the blank 68
fill in the blank 69
fill in the blank 70
fill in the blank 71

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!