Question: Problem 9 - 1 2 ( Algorithmic ) Assume that the activity time estimates ( in days ) for the swimming pool construction project are

Problem 9-12(Algorithmic)
Assume that the activity time estimates (in days) for the swimming pool construction project are as follows:
Activity Optimistic Most Probable Pessimistic
A 234
B 159
C 249
D 4710
E 258
F 345
G 378
H 168
I 267
What are the critical activities? If necessary, round your answers to two decimal places. If your answer is zero, enter 0.
Activity Expected Time Variance
A fill in the blank 1
3
fill in the blank 2
0.11
B fill in the blank 3
5
fill in the blank 4
1.78
C fill in the blank 5
4.50
fill in the blank 6
1.36
D fill in the blank 7
7
fill in the blank 8
1.00
E fill in the blank 9
5
fill in the blank 10
1.00
F fill in the blank 11
4
fill in the blank 12
0.11
G fill in the blank 13
6.5
fill in the blank 14
0.69
H fill in the blank 15
5.5
fill in the blank 16
1.36
I fill in the blank 17
5.5
fill in the blank 18
0.69
Earliest Latest Earliest Latest Critical
Activity Start Start Finish Finish Slack Activity
A fill in the blank 19
0
fill in the blank 20
fill in the blank 21
3
fill in the blank 22
fill in the blank 23
B fill in the blank 25
fill in the blank 26
fill in the blank 27
fill in the blank 28
fill in the blank 29
C fill in the blank 31
fill in the blank 32
fill in the blank 33
fill in the blank 34
fill in the blank 35
D fill in the blank 37
fill in the blank 38
fill in the blank 39
fill in the blank 40
fill in the blank 41
E fill in the blank 43
fill in the blank 44
fill in the blank 45
fill in the blank 46
fill in the blank 47
F fill in the blank 49
fill in the blank 50
fill in the blank 51
fill in the blank 52
fill in the blank 53
G fill in the blank 55
fill in the blank 56
fill in the blank 57
fill in the blank 58
fill in the blank 59
H fill in the blank 61
fill in the blank 62
fill in the blank 63
fill in the blank 64
fill in the blank 65
I fill in the blank 67
fill in the blank 68
fill in the blank 69
fill in the blank 70
fill in the blank 71
Critical Path:
What is the expected time to complete the project? If necessary, round your answer to two decimal places.
E(T)= fill in the blank 74
days
Based only on critical path, what is the estimated probability that the project can be completed in 25 or fewer days?
Variance = fill in the blank 75
. If necessary, round your answers to two decimal places.
Using the normal distribution, z = fill in the blank 76
. If necessary, round your answers to two decimal places. If negative answer is required, enter the minus sign before the number.
Probability of 25 days or less is fill in the blank 77
. If necessary, round your answers to four decimal places. Note: Use Appendix B to identify the probability.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!