Question: Problem 9-04 (Algorithmic) The activity times (in months) for the following project network: D E F G Activity Time B 8 2 5 6 4

Problem 9-04 (Algorithmic) The activity times (in months) for the following project network: D E F G Activity Time B 8 2 5 6 4 3 5 D G Start E Finish F a. Find the critical path. A-D-G b. The project must be completed in 1/2 years. Do you anticipate difficulty in meeting the deadline? Explain. The critical path activities require months to complete. Thus the project should be completed in years