Question: Given is a Project with network diagram and activity times as shown below. Activity A B C D E F G H I J Time

Given is a Project with network diagram and activity times as shown below.

Activity

A

B

C

D

E

F

G

H

I

J

Time (wks)

11

2

6

12

9

16

5

2

8

5

a) The Earliest Start (ES) time of Activity I = _____1 weeks b) The Latest Start (LS) time of Activity B = _____2 weeks c) The Slack time of Activity C = ____ 3 weeks d) The Earliest Finish (EF) time of Activity H = ____ 4 weeks e) The Latest Finish (LF) time of Activity B = ____ 5 weeks f) The Project Completion time = ____ 6 weeks

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!