Question: Given is a Project with network diagram and activity times as shown below. Activity A B C D E F G H I J Time
Given is a Project with network diagram and activity times as shown below.
| Activity | A | B | C | D | E | F | G | H | I | J |
| Time (wks) | 11 | 2 | 6 | 12 | 9 | 16 | 5 | 2 | 8 | 5 |
a) The Earliest Start (ES) time of Activity I = _____1 weeks b) The Latest Start (LS) time of Activity B = _____2 weeks c) The Slack time of Activity C = ____ 3 weeks d) The Earliest Finish (EF) time of Activity H = ____ 4 weeks e) The Latest Finish (LF) time of Activity B = ____ 5 weeks f) The Project Completion time = ____ 6 weeks