Question: Problem 9-05 (Algorithmic) Consider the Western Hills Shopping Center project summarized by Figure 9.6 and Table 9.2. FIGURE 9.6 WESTERN HILLS SHOPPING CENTER PROJECT

Problem 9-05 (Algorithmic) Consider the Western Hills Shopping Center project summarized byFigure 9.6 and Table 9.2. FIGURE 9.6 WESTERN HILLS SHOPPING CENTER PROJECTNETWORK WITH LATEST START AND LATEST FINISH TIMES SHOWN IN EACH NODE

Problem 9-05 (Algorithmic) Consider the Western Hills Shopping Center project summarized by Figure 9.6 and Table 9.2. FIGURE 9.6 WESTERN HILLS SHOPPING CENTER PROJECT NETWORK WITH LATEST START AND LATEST FINISH TIMES SHOWN IN EACH NODE A 0 5 5 0 5 A E 5 6 F 6 10 1 5 6 4 6 10 D 5 7 G 10 24 2 8 10 14 10 24 C 5 9 H 9 21 24 26 Start Finish 4 8 12 12 12 24 2 24 26 B 0 7 7 5 12 Table 9.2 ACTIVITY SCHEDULE FOR THE WESTERN HILLS SHOPPING CENTER PROJECT Table 9.2 ACTIVITY SCHEDULE FOR THE WESTERN HILLS SHOPPING CENTER PROJECT Earliest Latest Earliest Latest Start Start Finish Finish Slack Critical Activity (ES) (LS) (EF) (LF) (LS-ES) Path? A 0 0 5 5 0 Yes B C D E 0 5 7 12 5 5 8 9 12 3 5 8 10 3 5 5 6 0 Yes F 6 6 10 10 0 Yes G 10 10 24 24 0 Yes H 9 12 21 24 3 I 24 24 26 26 0 Yes Suppose the project has been underway for seven weeks. Activities A and E have been completed. Activity F has commenced but has three weeks remaining. Activities C and D have not started yet. Activity B has two weeks remaining (it was not started until week 2). Update the activity schedule for the project. In particular, how has the slack for each activity changed? If your answer is zero enter "0". Activity A B C FL H G H 1001-000-31 0000*000* * * 0000-000+ 3 1 UPDATED ACTIVITY SCHEDULE FOR THE WESTERN HILLS SHOPPING CENTER PROJECT Latest Earliest Latest Finish (LF) Slack (LS-ES) Path? 15-11-0 0000-000*** Yes Yes Critical

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Understanding the Project Schedule In this project we are dealing with a scheduling network for the Western Hills Shopping Center project The schedule shows activities A B C etc their early start ES l... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Mathematics Questions!