Question: Problem 9-05 (Algorithmic) Consider the Western Hills Shopping Center project summarized by Figure 9.6 and Table 9.2. Earliest Latest Earliest Latest Start Start Finish Finish

Problem 9-05 (Algorithmic) Consider the Western Hills Shopping Center project summarized by Figure 9.6 and Table 9.2. Earliest Latest Earliest Latest Start Start Finish Finish Slack Critical Activity (ES) (LS) (EF) (LF) (LSES) Path? A 0 0 5 5 0 Yes B 0 3 9 12 3 C 5 9 8 12 4 D 5 8 7 10 3 E 5 5 6 6 0 Yes F 6 6 10 10 0 Yes G 10 10 24 24 0 Yes H 9 12 21 24 3 I 24 24 26 26 0 Yes Suppose the project has been underway for seven weeks. Activities A and E have been completed. Activity F has commenced but