Question: Problem 9-06 (Algorithmic) Consider the following project network and activity times (in weeks): H A D F Start Finish B E G A B D

Problem 9-06 (Algorithmic) Consider the followingProblem 9-06 (Algorithmic) Consider the following

Problem 9-06 (Algorithmic) Consider the following project network and activity times (in weeks): H A D F Start Finish B E G A B D E F G H Activity Time 6 4 7 4 7 4 10 8 d. Can activity G be delayed without delaying the entire project? If so, by how many weeks? Yes If "No" enter "0". 3 X weeks. e. What is the schedule for activity C? Enter "O" if your answer is zero. Schedule for activity C Earliest Start 4 X Latest Start Earliest Finish Latest Finish