Question: Problem 9-07 (Algorithmic) Embassy Club Condominium, located on the west coast of Florida, is undertaking a summer renovation of its main building. The project is


Problem 9-07 (Algorithmic) Embassy Club Condominium, located on the west coast of Florida, is undertaking a summer renovation of its main building. The project is scheduled to begin May 1, and a September 1 (17-week) completion date is desired. The condominium manager identified the following renovation activities and their estimated times: Immediate Predecessor Activity Time a. Which project network is correct? b. What are the cntical activities? G. What activity has the most slack time? d. Will the praject be completed by September 1? If your answer is zero enter "o". Project Completion Time Is weeks. If your answer is zero enter "0". Critical Activity ivity Earliest Start Latest Start Earliest Finish Latest Finish Slack Activity I am 0