Question: PROBLEM A project has a sequence of 1 0 activities with the following characteristics: table [ [ , , Time Estimate in Weeks ]

PROBLEM
A project has a sequence of 10 activities with the following characteristics:
\table[[,,Time Estimate in Weeks],[Activity,\table[[Preceding],[activity]],\table[[Carla's],[Estimate (Ta)]],\table[[Tim's Estimate],[(Tb)]]],[A,-,4,5],[B,-,1,1.5],[C,A,2,3],[D,A,3,4],[E,A,2,3],[F,C,1.5,2],[G,D,1.5,3],[H,B, E,2.5,3.5],[I,H,1.5,2],[J,F, G, I,1,2]]
Two people, Carla and Tim have prepared the estimate of the time for each task and have presented their inputs in Estimate-1 and Estimate-2, respectively.
(a) Using the above table, determine the least amount of time needed to complete the project as per Carla's and Tim's respective estimates. In doing so, identify the critical tasks in achieving these times as per Carla's data and Tim's data. Compare their times and determine whose estimated time is shorter.
(b) As a manager, you give these estimates to your specialist, Martha. She suggests using the following formula to determine the estimated time for each task:
Tc=1.5Ta+1.4Tb+0.13
Prepare a third column with the above formula for each task and then determine the least amount of time needed to complete the project and the critical tasks/path as per Martha. Finally, compare the times predicted by Carla's, Tim's and Martha's estimates and determine the shortest time and the l
PROBLEM
A project has a sequence of 10 activities with the following characteristics:
\table[[,,Time Estimate in Weeks],[Activity,\table[[Preceding],[activity]],\table[[Carla's],[Estimate (Ta)]],\table[[Tim's Estimate],[(Tb)]]],[A,-,4,5],[B,-,1,1.5],[C,A,2,3],[D,A,3,4],[E,A,2,3],[F,C,1.5,2],[G,D,1.5,3],[H,B, E,2.5,3.5],[I,H,1.5,2],[J,F, G, I,1,2]]
Two people, Carla and Tim have prepared the estimate of the time for each task and have presented their inputs in Estimate-1 and Estimate-2, respectively.
(a) Using the above table, determine the least amount of time needed to complete the project as per Carla's and Tim's respective estimates. In doing so, identify the critical tasks in achieving these times as per Carla's data and Tim's data. Compare their times and determine whose estimated time is shorter.
(b) As a manager, you give these estimates to your specialist, Martha. She suggests using the following formula to determine the estimated time for each task:
Tc=1.5Ta+1.4Tb+0.13
Prepare a third column with the above formula for each task and then determine the least amount of time needed to complete the project and the critical tasks/path as per Martha. Finally, compare the times predicted by Carla's, Tim's and Martha's estimates and determine the shortest time and the largest time needed.
Criteria to pass the project:
For each part of the question
The PERT analysis diagram is clearly drawn
The estimates are clearly indicated
The calculations are correcta
Criteria to pass the project:
For each part of the question
The PERT analysis diagram is clearly drawn
The estimates are clearly indicated
The calculations are correct
 PROBLEM A project has a sequence of 10 activities with the

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!