Question: 04) The below table defines the activities within a small project. (1) Draw the network diagram, (ii) Calculate the overall project completion time and identify

04) The below table defines the activities within

04) The below table defines the activities within a small project. (1) Draw the network diagram, (ii) Calculate the overall project completion time and identify which activities are critical (critical path). Preceding Time estimate weeks Activity activity Optimistic Most likely Pessimistic 5 12 1 1.5 5 A 2 3 E A 4 - B 3 4 D A 4 11 A 2 3 4 F 1.5 2 2.5 G D 1.5 3 4.5 H 2.5 3.5 7.5 BE H F,GI 1.5 2.5 2 2 1 3