Question: Problem (Ch. 19, Project Management) Consider the project with the following dependency matrix. Predecessor Activity 1 2 3 4 5 6 7 8 1 2

Problem (Ch. 19, Project Management) Consider the

Problem (Ch. 19, Project Management) Consider the project with the following dependency matrix. Predecessor Activity 1 2 3 4 5 6 7 8 1 2 2 2 4,5 3,6 6,7 Activity Time (Days) 2 5 7 3 4 6 3 8 a) Draw an activity network diagram and compute the earliest completion time of the project using EST/ECT. (20 pts/100) b) Draw a Gantt chart for this project including slack times. (20 pts/100)