Question: Assignment - Project Management Consider the following project as stated below: # Activity Predecessor Duration ES EF LS LF 1 START None 0 2 A
| Assignment - Project Management | ||||||||
| Consider the following project as stated below: | ||||||||
| # | Activity | Predecessor | Duration | ES | EF | LS | LF | |
| 1 | START | None | 0 | |||||
| 2 | A | 1 | 10 | |||||
| 3 | B | 2,5 | 12 | |||||
| 4 | C | 3 | 9 | |||||
| 5 | D | 1 | 5 | |||||
| 6 | E | 5,8 | 7 | |||||
| 7 | F | 6 | 6 | |||||
| 8 | G | 1 | 3 | |||||
| 9 | H | 8 | 4 | |||||
| 10 | I | 9 | 6 | |||||
| 11 | END | 4,7,10 | 0 | |||||
| make an Excel Solution based on the above table. | ||||||||
| Question | ||||||||
| 1 | What is the ES, EF, LS,LF, and Slack for all activities? | |||||||
| 2 | What is the Critical Path | |||||||
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock