Question: Assignment - Project Management Consider the following project as stated below: # Activity Predecessor Duration ES EF LS LF 1 START None 0 2 A

Assignment - Project Management
Consider the following project as stated below:
# Activity Predecessor Duration ES EF LS LF
1 START None 0
2 A 1 10
3 B 2,5 12
4 C 3 9
5 D 1 5
6 E 5,8 7
7 F 6 6
8 G 1 3
9 H 8 4
10 I 9 6
11 END 4,7,10 0
make an Excel Solution based on the above table.
Question
1 What is the ES, EF, LS,LF, and Slack for all activities?
2 What is the Critical Path

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!