Question: Problem Consider the following project which for simplicity is assumed to have 1 0 activities with the following data: table [ [ table

Problem
Consider the following project which for simplicity is assumed to have 10 activities with the following data:
\table[[\table[[Work],[package]],A,B,C,D,E,F,G,H,J,K],[\table[[Completion],[time]],t1,t2,t3,t4,t5,t6,t7,t8,t9,t10],[\table[[Budgeted cost],[BC]],50,50,100,150,150,150,150,120,60,50]]
At the end of time t6 it is reported that the situation is as follows:
\table[[Work package,A,B,C,D,E,F],[\table[[Percent],[complete]],100,100,100,100,60,40],[\table[[Actual cost AC]],60,80,120,160,100,100]]
Find the schedule variance and cost variance, comment on the project cost and running?
Problem Consider the following project which for

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!