Question: problem manually and using primavera. The following eight activities constitute an overall bar chart portrayal of a fourmonth project. After one and one-half months, Activities
problem manually and using primavera. The following eight activities constitute an overall bar chart portrayal of a fourmonth project. After one and one-half months, Activities A,B,D, and half of E were completed, for a cost of $8,000. For this project, using carned value concepts, determine the schedule variance and the cost variance. State if the project is over or under budget and if it is ahead of or behind schedule
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
