Question: problem manually and using primavera. The following eight activities constitute an overall bar chart portrayal of a fourmonth project. After one and one-half months, Activities

 problem manually and using primavera. The following eight activities constitute an

problem manually and using primavera. The following eight activities constitute an overall bar chart portrayal of a fourmonth project. After one and one-half months, Activities A,B,D, and half of E were completed, for a cost of $8,000. For this project, using carned value concepts, determine the schedule variance and the cost variance. State if the project is over or under budget and if it is ahead of or behind schedule