Question: Problem REQUIRED: 1. Draw a Gantt chard by using MSP 2. Assuming 5-day week, find the critical path and project duration 3, Given that each

Problem

Problem REQUIRED: 1. Draw a Gantt chard by using

REQUIRED:

1. Draw a Gantt chard by using MSP

2. Assuming 5-day week, find the critical path and project duration

3, Given that each resource is assigned 100% to each task, identify the resource constraints

4, Using the Microsoft Project default, level the resources and determine the new project duration and critical path

Activity Immediate Predecessor Resource Used Activity Duration (Days) 2 2 X,Y A B A w NN X A 3 X D B,C 4 E D 3 XY W,X W,X,Y X,Y F D 1 G E,F 2