Question: Problem setting: -- Bill of material for A (lead time of 1 week): Part Number Low-level Code Quantity Required Lead Time (weeks) B 1 3

Problem setting:
-- Bill of material for A (lead time of 1 week):
Part Number Low-level Code Quantity Required Lead Time (weeks)
B 1 3 1
C 2 1 1
D 2 1 2
D 2 2 2
-- Requirement in week 5: 150
-- Projected available prior week 1:
A 20
B 30
C 120
D 80
-- Order lot size: no restriction
Question:
Complete the following table:
Low-level Code Part Number Week
1 2 3 4 5
0 A Gross Requirements 150
Scheduled Receipts
Projected Available 20
Net Requirements
Planned Order Receipt
Planned Order Release
1 B Gross Requirements
Scheduled Receipts
Projected Available 30
Net Requirements
Planned Order Receipt
Planned Order Release
2 C Gross Requirements
Scheduled Receipts
Projected Available 120
Net Requirements
Planned Order Receipt
Planned Order Release
2 D Gross Requirements
Scheduled Receipts
Projected Available 80
Net Requirements
Planned Order Receipt
Planned Order Release

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!