Question: Problem Solving Activity * Goodm School of Bus Brock Unive This table contains information related to major activities of a research project. Use the information

Problem Solving Activity * Goodm School of Bus

Problem Solving Activity * Goodm School of Bus Brock Unive This table contains information related to major activities of a research project. Use the information to do the following: Immediate Predecessor Activity Expected Time (days) a a a 5 8 2 7 3 6 a) Draw a precedence diagram using AON. b) Use CPM to find the critical path. c) Determine the expected length of the project. -1.31. . 9 h 17 k end OPER 2P91: Operations Management - Fall 2020