Question: Problem Solving: Capacity Planning XYZ Company has 60 workers distributed equally in 3 shift in the assembly area . Each worker enjoys an hour and
Problem Solving: Capacity Planning
XYZ Company has 60 workers distributed equally in 3 shift in the assembly area . Each worker enjoys an hour and 15 minutes.The rate of output per worker/machine is 25 pcs. The man machine ratio is 1:1 and presently they have 27 machines. They work 5 days in a week and considers 4 weeks in a month.
a.Find the available capacity if a power failure occurred from 8 am to 10:35 am of Day 2 of Week 5.
b. Find the max. capacity for 1 quarter.
c.What is the available capacity for 1 month if power shutdown occurred from 6:00 to 9:35 pm on days 3,4,5 of week 2
d.Find the lost capacity if a material shortage occurred from 6:00 pm to 10:45 pm of Day 4
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts