Question: Problem Statement A 5 - m - high highway embankment is to be constructed over a landfill that has a fine - grained soil cover

Problem Statement
A 5-m-high highway embankment is to be constructed over a landfill that has a fine-grained soil
cover underlain by a soil mixture with a total thickness ranging from 5.0 to 8.2 m . This soil
mixture includes primarily silts and clays with construction waste (concrete blocks, brick
fragments, etc.). At certain locations, there are voids and loose pockets within the landfill.
Standard penetration tests performed prior to ground improvement indicate SPT values ranging
from about 5 to 20 with an average of 10. The predicted settlement ranged from 140 to 274
mm . Dynamic compaction is selected to reduce the anticipated total and differential settlements.
The required SPT N value after improvement should be at least 20. The surface of the
landfill is strong enough to support the dynamic compaction equipment. Leachate inside the
landfill was at a relatively shallow depth (approximately 2.5 m from the existing surface).
To minimize the generation of excess pore water pressure, multiple pass construction may be
needed. The contractor has an 18.2- ton tamper that has a diameter of 1.5 m and a height of
1.5 m . You are requested to provide a preliminary design for the dynamic compaction project
and estimate the settlement after compaction.
Problem Statement A 5 - m - high highway

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!