Question: Problem Statement A 5 - m - high highway embankment is to be constructed over a landfill that has a fine - grained soil cover
Problem Statement
A mhigh highway embankment is to be constructed over a landfill that has a finegrained soil
cover underlain by a soil mixture with a total thickness ranging from to m This soil
mixture includes primarily silts and clays with construction waste concrete blocks, brick
fragments, etc. At certain locations, there are voids and loose pockets within the landfill.
Standard penetration tests performed prior to ground improvement indicate SPT values ranging
from about to with an average of The predicted settlement ranged from to
mm Dynamic compaction is selected to reduce the anticipated total and differential settlements.
The required SPT value after improvement should be at least The surface of the
landfill is strong enough to support the dynamic compaction equipment. Leachate inside the
landfill was at a relatively shallow depth approximately m from the existing surface
To minimize the generation of excess pore water pressure, multiple pass construction may be
needed. The contractor has an ton tamper that has a diameter of m and a height of
m You are requested to provide a preliminary design for the dynamic compaction project
and estimate the settlement after compaction.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock